MSProjHelp Needed.
I have a project setup with Generic resources assigned to the tasks. I have
all tasks set at fixed duration and to start asap. I have the resources set
up with various allocations from 25%-100%. For some reason when I plug in the
tasks, dependencies and resources and then hit level I get overallocation
errors for almost all tasks. I tried taking out the dependencies and that
doesn't help just allocates all hours in the first project month. When
looking at the resource usage by month, it doesn't appear ms project is
spreading the hours evenly. Some resources had 1000 hours in one month. I
have tried changing from fixed duration to fixed units etc. with no luck.
Specifically, The manager resource is set for 50% allocation or 4 hours
daily. when I type a task in for 6 hours shouldn't the task be spread across
2 days and not show as overallocated? It shows 1.5 day duration, but still
shows the resource to be overallocated for that task.
thanks.
all tasks set at fixed duration and to start asap. I have the resources set
up with various allocations from 25%-100%. For some reason when I plug in the
tasks, dependencies and resources and then hit level I get overallocation
errors for almost all tasks. I tried taking out the dependencies and that
doesn't help just allocates all hours in the first project month. When
looking at the resource usage by month, it doesn't appear ms project is
spreading the hours evenly. Some resources had 1000 hours in one month. I
have tried changing from fixed duration to fixed units etc. with no luck.
Specifically, The manager resource is set for 50% allocation or 4 hours
daily. when I type a task in for 6 hours shouldn't the task be spread across
2 days and not show as overallocated? It shows 1.5 day duration, but still
shows the resource to be overallocated for that task.
thanks.