J
J Baird
I have a schedule, where I've renumbered the WBS numbers for selected tasks,
on a regular basis. ([Project][Wbs][Renumber][Select Tasks])
All of a sudden, in the [WBS Renumber] dialog box, the [Selected Tasks]
option is greyed out (the [Entire Project] option is still selectable).
Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.
To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.
I can't find anything in the knowledge base about this. Has anyone seen
this behavior before, and if so, do you know what caused it?
on a regular basis. ([Project][Wbs][Renumber][Select Tasks])
All of a sudden, in the [WBS Renumber] dialog box, the [Selected Tasks]
option is greyed out (the [Entire Project] option is still selectable).
Nothing else has changed...the WBS settings and Code Definition are still
the same as when the [Selected Tasks] option was available.
To try to fix the problem , I selected [Project][Wbs][Renumber][Entire
Project], to renumber the entire project, hoping that would bring back the
[Selected Tasks] option, but it didn't.
I can't find anything in the knowledge base about this. Has anyone seen
this behavior before, and if so, do you know what caused it?