Can't see assignments for resources from other projects in project pro

K

kkorsun

Hi. I use Project Pro 2007 and Project Server 2007. I have resource
pool and several projects with assignments. I open any project in
Resources Usage view I don't see assigments from other projects (see
only from current project). In PWA is everything ok. All assigments
across all projects, where resourse is used, is showing. And
availability calculating in PWA is correct. But in Project Pro
availability is invalid, because it don't calculate resource usage in
other projects.
I also noticed that problem started in Build Team from Enterprise
dialog box. Resource using in other projects is 0h if resource is in
project team (button Graphs). But it's everything ok for other
resources (not in current project team). Just add resource from
enterprise and Graphs show me that this resource have 0h in other
projects.

It look like after adding resource to project team usage this for
resource in other projects disappers.

Any ideas?
 
D

Dale Howard [MVP]

kkorsun --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is shutting
down. To answer your question, you must do the following:

1. Launch Microsoft Project Professional 2007.
2. In the Login dialog, make sure you select the "Load Summary Resource
Assignments" option
3. Click the OK button to complete the login process

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top