Can't see data from custom field added to the "My Assignments" vie

R

Rick F.

I added a custom text field to the "My Assignments" view so it will show up
in My Tasks for timesheet users to see. However, when clicking on My Tasks,
the field is there, but none of the data in that field is visible.
Similarily, I can add data into the field in My Tasks, but it won't transfer
over to the project schedule when the task is submitted. Anyone know how to
at least get custom fileds to show when added to the my assignments view?
 
D

Dale Howard [MVP]

Rick F --

Go to Server Settings - Custom Enterprise Field Definition. Click the name
of the Task field you created to open it for editing. In the Calculation
for Assignment Rows section, did you remember to select the "Roll down,
unless manually specified" option? If not, select this option and click the
Save button. That should solve your problem. Also, you failed to mention
your current level of Service Packs and Cumulative Updates on your Project
Server 2007 system. It would help if we knew that when answering your
future questions. Hope this helps.
 