Can't see Tasks

S

Steve Lundwall

I have a user who cannot see his tasks in PWA. The project name shows up
under Projects. I've republished the project. I've set him as an
Administrator to everything. However, none of his tasks show up when
selecting Tasks (and he has a bunch of tasks). Any ideas?

Steve
 
S

Scott Morrissey

Make sure that the "Booking Type" field for this resource on the project is
set to "Committed". If it is "Proposed", the tasks will not go to his
timesheet. The Booking Type column can be inserted into the Resource Sheet
view to observe / change the value. Hope this helped.
 
F

Fabio Cabral

Steve,

In the Task Pane, check if the option "All Tasks" is selected and also check
if there is no filter in action.
Hope that helps.

Regards,

Cabral
 
S

Steve Lundwall

All Tasks are shown and no Filters are in place. Still no luck. When I
assign a task it also doesn't show up on this PWA Home Page (Doesn't says
"You have 2 new tasks assigned to you.") And I did check the email address.

Any other ideas? Thanks.

Steve
 