Can't see time in an Admin project on the Resource assignment view

J

Josh

I'm implementing project server to track all resource time includeing
non-project time. I'm using Administrative projects to track this time, but
I need to be able to produce a report on all time enter for a specific
resource for a two week span. So far, I'm using Resource Assignment Summary
view to do this, but it's only showing the time entered into actual projects,
none of the time entered into the admin projects.

Any ideas???
 
M

Marc Soester [MVP]

Hi Josh,

I assume that you are using Project Server 2003? If so you can report
against time entered by using the Portfolio Analyser within Project Server
2003.
Hope this pushes you into the right direction
Let me know ifyou have more questions
Thanks
 
J

Josh

Thanks for the quick answer Marc, but I was under the understanding that
there wasn't a way to get weekly timeframes in the Portfolio Analyzer.

Please correct me if I'm wrong.

Thanks,
Josh
 