I have a milestone activity that I can't change to 100% Complete. All of its
predecessors are 100% so I can not see why this will can't be set.
What is even stranger is that I encounter an error that my actuals are out
of sync message when I change the milestone task to 100%. There is no
resource assigned to the task, and actual work, remaining dur and remaining
work all equal 0.
Some indicators by some task informs me that the assignments have changed so
when I go to collaborate, it asks me to resync. Upon selecting Y, my
milestone goes back to 0.
predecessors are 100% so I can not see why this will can't be set.
What is even stranger is that I encounter an error that my actuals are out
of sync message when I change the milestone task to 100%. There is no
resource assigned to the task, and actual work, remaining dur and remaining
work all equal 0.
Some indicators by some task informs me that the assignments have changed so
when I go to collaborate, it asks me to resync. Upon selecting Y, my
milestone goes back to 0.