Can't Set % Complete On Milestone To 100

B

Barry

I have a milestone activity that I can't change to 100% Complete. All of its
predecessors are 100% so I can not see why this will can't be set.

What is even stranger is that I encounter an error that my actuals are out
of sync message when I change the milestone task to 100%. There is no
resource assigned to the task, and actual work, remaining dur and remaining
work all equal 0.

Some indicators by some task informs me that the assignments have changed so
when I go to collaborate, it asks me to resync. Upon selecting Y, my
milestone goes back to 0.
 
D

Dale Howard [MVP]

Barry --

You need to install SR-1 on your Project Server and on each of your
computer's. What you are describing is a known bug that was fixed in SR-1.
Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top