I am setting up a Project 2003 file for a project involving inspections of 30
facilities. I would like to track them a decrete groups of tasks in the same
file. Each facility consists of the same tasks repeated with only the start
date different. I created the tasks and timelines for the first facility, got
the dependencies and constraints straight, formated the bars and labels, etc.
I then copied that group of tasks, changed the facility label for each
facility. When I tried to adjust the start date for the second and third
groups of tasks, ALL the start dates changed. I checked and can't find any
dependencies to other groups of tasks. I tried unlinking and relinking them.
They are all outdented as far as they will go.
Anyone have any ideas how to get these 30 groups of tasks to operate
independently? Thanks in advance for any help.
facilities. I would like to track them a decrete groups of tasks in the same
file. Each facility consists of the same tasks repeated with only the start
date different. I created the tasks and timelines for the first facility, got
the dependencies and constraints straight, formated the bars and labels, etc.
I then copied that group of tasks, changed the facility label for each
facility. When I tried to adjust the start date for the second and third
groups of tasks, ALL the start dates changed. I checked and can't find any
dependencies to other groups of tasks. I tried unlinking and relinking them.
They are all outdented as far as they will go.
Anyone have any ideas how to get these 30 groups of tasks to operate
independently? Thanks in advance for any help.