P
PM
We want to capture actual hours worked via PWA but NOT have that impact the
forecast allocation % already set/entered in EPM. Today in Server 2003, when
entering in acutal hours, the forecasts allocations/hours change. E.g. My
forecast hours for M-F was 6 hours on a project and 2 hours on maintenance
support. I enter 6 & 2 for Mon & Tues, but on Wed, I only enter 4 hours of
project work, my projected hours/allocation % from that day onwards will
automatically get re-calculated becuase I didn't work enough hours as what
was projected. I DON'T want the projection to change so even if there is a
way to fake out EPM and create a new field to capture the actual hours in a
way that projection doesn't change, that's what I'm in search for (or any
other solution that would get me this end result). Please help!
forecast allocation % already set/entered in EPM. Today in Server 2003, when
entering in acutal hours, the forecasts allocations/hours change. E.g. My
forecast hours for M-F was 6 hours on a project and 2 hours on maintenance
support. I enter 6 & 2 for Mon & Tues, but on Wed, I only enter 4 hours of
project work, my projected hours/allocation % from that day onwards will
automatically get re-calculated becuase I didn't work enough hours as what
was projected. I DON'T want the projection to change so even if there is a
way to fake out EPM and create a new field to capture the actual hours in a
way that projection doesn't change, that's what I'm in search for (or any
other solution that would get me this end result). Please help!