D
DWall
I want to be able to capture the actual amount of work a task took and
when I mark the task complete the actual amount of work entered doesn't
get recalculated to match the planned work.
Does anyone know how to do this?
Example:
A task has a duration of 5 days and 40 hours of work. The person
doing the tasks spends 5 hrs on the task. We enter 5 in the actual work
column and the % complete changes to 13%; which is correct. Then if
they enter 100 into the %complete column the actual work changes to 40
hrs, which isn't true, it was 5 hours. How can I capture the real
value?
when I mark the task complete the actual amount of work entered doesn't
get recalculated to match the planned work.
Does anyone know how to do this?
Example:
A task has a duration of 5 days and 40 hours of work. The person
doing the tasks spends 5 hrs on the task. We enter 5 in the actual work
column and the % complete changes to 13%; which is correct. Then if
they enter 100 into the %complete column the actual work changes to 40
hrs, which isn't true, it was 5 hours. How can I capture the real
value?