J
JJKEN
Is there a way to capture actual finish dates that are different than the
planned finish dates when entering a task as 100% complete?
In other words, is their a way around Project automatically assuming that
the task was completed on the planned finish date when entering 100% complete?
Or do you always need to adjust the Start/Finish dates to reflect the latest
thinking?
planned finish dates when entering a task as 100% complete?
In other words, is their a way around Project automatically assuming that
the task was completed on the planned finish date when entering 100% complete?
Or do you always need to adjust the Start/Finish dates to reflect the latest
thinking?