Sorry if this has been asked before, but I have searched the forum and not
found an answer that fits. I have been tasked to produce a cashflow for a
construction project. I know how to put the money in as a fixed cost against
each activity. I also know that you can allocate costs against the start,
finish or pro rata against the duration. No problems so far. What I am
struggling with is how do I simulate payment delays, ie you complete the work
but do not get paid for say 3 weeks later?. Also, I know how to use the
analyze timescale data in excel button, but is there a better way, that keeps
the information live ie if the contract bars move etc, without having to re
export as I find that I have to do some work on the excel file after the
export in order that the information is more readable. VBA has been mentioned
to me but I am a real novice in this and do not have the resources inhouse to
explore this. I have linked excel and MSP before and have found that the
whole thing becomes ver cumbersome and loses the connection when you relocate
files.
Any help would be appreciated
Andrew
Sorry if this has been asked before, but I have searched the forum and not
found an answer that fits. I have been tasked to produce a cashflow for a
construction project. I know how to put the money in as a fixed cost against
each activity. I also know that you can allocate costs against the start,
finish or pro rata against the duration. No problems so far. What I am
struggling with is how do I simulate payment delays, ie you complete the work
but do not get paid for say 3 weeks later?. Also, I know how to use the
analyze timescale data in excel button, but is there a better way, that keeps
the information live ie if the contract bars move etc, without having to re
export as I find that I have to do some work on the excel file after the
export in order that the information is more readable. VBA has been mentioned
to me but I am a real novice in this and do not have the resources inhouse to
explore this. I have linked excel and MSP before and have found that the
whole thing becomes ver cumbersome and loses the connection when you relocate
files.
Any help would be appreciated
Andrew