A
Andrew
I am trying to create a simple cashflow for a construction proogramme. I have
elemenatal costs only, ie substructure, superstructure, finishes etc... I
have a detailed construction programme. I have tried to copy the fields to
excel so that I can obtain the workdays in each element, with th thoght of
allocating the elemental cost divided by the workdays as a fixed cost to a
resource which I can then allocate to each activity. The first question is
when I copy the duration field it comes up as dys.in excel I cannot seem to
autosum these values, is there a way of translating the field to a number.
The second question is am I wasting my time with this method and is there an
easier way, I want to use MSp for this purpose and not use a different pice
of software.
Looking forward to any assistance in this
Regards
Andrew
elemenatal costs only, ie substructure, superstructure, finishes etc... I
have a detailed construction programme. I have tried to copy the fields to
excel so that I can obtain the workdays in each element, with th thoght of
allocating the elemental cost divided by the workdays as a fixed cost to a
resource which I can then allocate to each activity. The first question is
when I copy the duration field it comes up as dys.in excel I cannot seem to
autosum these values, is there a way of translating the field to a number.
The second question is am I wasting my time with this method and is there an
easier way, I want to use MSp for this purpose and not use a different pice
of software.
Looking forward to any assistance in this
Regards
Andrew