E
Ed Hanna
Yesterday, I was conducting an introductory MS Project class and ran across some MS Project Professional behavior that I couldn't explain. On the Gantt Chart view, we were looking at the Cost Table as a place to enter Actual Cost. One of the students could not make entries in the Actual Cost column because it was grayed out.
I couldn't come up with an on-the-spot reason why it would act that way but thought that I could later try some things that might reproduce the condition. So far, I haven't been able to reproduce the behavior.
It was Project Professional 2003 and we were not connected to Project Server. We started with a new project schedule and entered 8-10 tasks and were exploring the basic operations (e.g. creating a task list, creating summary tasks, linking tasks, assigning resources to tasks, assigning costs to resources).
Does anyone know what might cause columns of data in MS Project to be grayed out?
Ed
I couldn't come up with an on-the-spot reason why it would act that way but thought that I could later try some things that might reproduce the condition. So far, I haven't been able to reproduce the behavior.
It was Project Professional 2003 and we were not connected to Project Server. We started with a new project schedule and entered 8-10 tasks and were exploring the basic operations (e.g. creating a task list, creating summary tasks, linking tasks, assigning resources to tasks, assigning costs to resources).
Does anyone know what might cause columns of data in MS Project to be grayed out?
Ed