B
Bill Mc
I would like to establish a practice where the PMO initially loads project
plans in Project Server 2007 in order to maintain some control over the
naming standards and site creation. In my scenario, a PM would might provide
the PMO with a plan already developed using Project Pro, the PMO would then
create the project in Project Center, with the correct naming and site
hierarchy. Then the PM would maintain the plan going forward.
The question I have is, with this scenario, am i asking for trouble
regarding the Owner, Assignment Owner and Status Manager fields? Do I need
to provide the PM's with practices to change these to their control after the
PMO has created the initial projects?
Thanks
plans in Project Server 2007 in order to maintain some control over the
naming standards and site creation. In my scenario, a PM would might provide
the PMO with a plan already developed using Project Pro, the PMO would then
create the project in Project Center, with the correct naming and site
hierarchy. Then the PM would maintain the plan going forward.
The question I have is, with this scenario, am i asking for trouble
regarding the Owner, Assignment Owner and Status Manager fields? Do I need
to provide the PM's with practices to change these to their control after the
PMO has created the initial projects?
Thanks