I’m trying to remove Overtime Work from the popup window you get when you
click Progress on the My Tasks page in PWA 2007.
I can edit both the My Tasks view and the Details view in Manage Views, but
neither place allows me to remove Overtime Work. I’ve also tried to edit the
Shared Web Part, but don’t see the option there.
Has anyone run across this? Any suggestions on what else to try?
Thanks in advance!
AB