Change all end dates at the same time

J

Jamie McJannett

Hi, we have a project with a few thousand repeat tasks which are set to
repeat every week/fortnight or month on a specific day of the week. the
main problem we have is that when the project was originally setup 2
years ago they made the end dates for all the tasks to be july 2009.
what we need to do is try to change the end date of all the tasks at the
same time instead of going through and manually changing each tasks end
date.

is this possible? and if so how might one do this?


Thankyou


Jamie McJannett
KaijaDesigns
 
J

John

Jamie McJannett said:
Hi, we have a project with a few thousand repeat tasks which are set to
repeat every week/fortnight or month on a specific day of the week. the
main problem we have is that when the project was originally setup 2
years ago they made the end dates for all the tasks to be july 2009.
what we need to do is try to change the end date of all the tasks at the
same time instead of going through and manually changing each tasks end
date.

is this possible? and if so how might one do this?


Thankyou


Jamie McJannett
KaijaDesigns

Jamie,
Try the Adjust Dates built-in macro. You should be able to find it on
the Analysis toolbar. At least that's where it is with Project 2003.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top