L
Lars Kragh-Hansen
In a Project Server2007 solution, I need to add the following functionality
to certain views in all projects in the enterprise:
When the finish date on a task or milestone is exceeded by the current date,
the colour of the element should be changed from the original colour to grey.
The PMs are not entering data regarding physical completion %, so using the
CompleteThrough condition is not an option.
TIA
Lars
to certain views in all projects in the enterprise:
When the finish date on a task or milestone is exceeded by the current date,
the colour of the element should be changed from the original colour to grey.
The PMs are not entering data regarding physical completion %, so using the
CompleteThrough condition is not an option.
TIA
Lars