Hari
I am using MS Project 2007 Pro. For the resource rate, the application uses
default resource cost rate table "A". How can I change this to table "B", so
next time when my PM's create schedules from enterprise template, the cost is
determined using table "B" automatically, instead of cost rate table "A"