Change default cost rate table

H

Hari

I am using MS Project 2007 Pro. For the resource rate, the application uses
default resource cost rate table "A". How can I change this to table "B", so
next time when my PM's create schedules from enterprise template, the cost is
determined using table "B" automatically, instead of cost rate table "A"
 
D

Dale Howard [MVP]

Hari --

You can't. Every new task assignment automatically uses the Cost Rate Table
A value. From there, you can change the rate in either the Task Usage view
or Resource Usage view. Hope this helps.
 