RChrisR said:
I need to be able to view data (task or resource usage view) per my
accounting periods which are different than a normal month. Any
suggestions?
RChrisR,
Unfortunately Project has never provided the functionality for user
defined accounting months. Consequently, the only way to easily view
accounting month data from Project is to export the data to another
application (e.g. Excel). This is doable via a VBA macro or if you are
using Project 2007, you could use the Visual Reports feature to export
the timescaled data and then arrange it into accounting months in Excel.
John
Project MVP