Change Default Standard Calendar?

D

Dee

Is there some way to change the default standard calendar
to include company holidays so I don't have to go in and
change working time on every new project I create? I'm
running Project 2002 Professional but not Project Server.
Thanks.
 
G

Gérard Ducouret

Hello Dee,
You'll have to change the Standard calendar in your Global.MPT file on your
HDD :
In the project containing your "customized" Standard calendar, do the
following :

Tools / Organizer... / Calendars / select your Standard and click the Copy
button toward the Global.MPT

Gérad Ducouret
 