K
Kirsty
Hi,
I am trying to change the duration and end dates of tasks in my MPP (2003,
no Project Server). There is only one resource assigned to any task. All
durations are estimate until completed. All tasks pretty much have a
predecessor.
Feature of each task:
* Fixed Units
* Effort driven
* Earned Value method is % complete
I want to update the duration and finish date, but the task may not have
been able to be worked on directly after its predecessor. Due to multiple
dependancies not able to be captured in the MPP, resources may work on any
task in any sequence, may stop working on a task for a few weeks, and return
to it.
I am only interested in how long a task took all up, and on what date that
task was finalised.
When we try to update the duration and actual finish date, 99% of the time,
the task will run from the Start date, and we end up with a much longer
duration than acutal. If we re-modify the duration to the actual amount of
time, then the finish date is much earlier than it actually was.
I am able to do this successfully with a different MPP (much simpler, only
10s of tasks, not 100s of tasks), and cannot figure out what is different
that is stopping me from making these modifications successfully.
Thanks in anticipation of any help or insight,
Kirsty
I am trying to change the duration and end dates of tasks in my MPP (2003,
no Project Server). There is only one resource assigned to any task. All
durations are estimate until completed. All tasks pretty much have a
predecessor.
Feature of each task:
* Fixed Units
* Effort driven
* Earned Value method is % complete
I want to update the duration and finish date, but the task may not have
been able to be worked on directly after its predecessor. Due to multiple
dependancies not able to be captured in the MPP, resources may work on any
task in any sequence, may stop working on a task for a few weeks, and return
to it.
I am only interested in how long a task took all up, and on what date that
task was finalised.
When we try to update the duration and actual finish date, 99% of the time,
the task will run from the Start date, and we end up with a much longer
duration than acutal. If we re-modify the duration to the actual amount of
time, then the finish date is much earlier than it actually was.
I am able to do this successfully with a different MPP (much simpler, only
10s of tasks, not 100s of tasks), and cannot figure out what is different
that is stopping me from making these modifications successfully.
Thanks in anticipation of any help or insight,
Kirsty