Change duration units to days?

B

btodag

How do I change my duration units from hours to days? For example, a task will take 4 hours, but my boss wants to see "days". How do I make it say .5days after I've done my entire project in hours? Can I apply it to the whole project?
 
M

Mike Glen

Hi btodag,

Welcome to this Microsoft Project newsgroup :)

Tools./Options.../Schedule tab/Duration is entered in: change to Days.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
G

Gérard Ducouret

Hello,
To change the duration unit of all the tasks already entered, use the
Format_Duration VBA procedure:
Tools / Macro / Macros... / Format_Duration / Run

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top