S
smck
I am working in Project 2003 and in the Gantt View the timescale label shows
14 Mar '10 I would like it to show Mar 14 '10 or 03/14/10. Is there a way to
change this? I tried Help but the change I am seeing is in the Calendar View
not the Gantt View. Also, the date on my computer is displaying as Mar 9 '10
but I can't seem to get the Gantt in that display.
Any help is appreciated.
Thanks
14 Mar '10 I would like it to show Mar 14 '10 or 03/14/10. Is there a way to
change this? I tried Help but the change I am seeing is in the Calendar View
not the Gantt View. Also, the date on my computer is displaying as Mar 9 '10
but I can't seem to get the Gantt in that display.
Any help is appreciated.
Thanks