Jean-Claude,
If the task had not any date constraint, when you force an end date, you
introduce a Finish Not Later than constraint and the Duration doesn't
change.
If the task already had a Start Not Earlier Than constraint, when you force
an end date, you introduce a Finish Not Later than constraint and the
Duration *change*.
Anyway, has Rod stated, forcing dates is counter-productive as Project can
no longer calculate them for you and you have to manually maintain them from
now on.
Hope this helps,
Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris
"Jean-Claude" <
[email protected]> a écrit dans le message
de news:
[email protected]...
When I change end date sometimes start date is recalculated and duration is
is not changed. and sometimes start date is not changed and duration is
recalculated.
I don't what I can do to have always the first instance : start date
recalculated and duration not changed.