L
Lars Kragh-Hansen
I need to change the font colour on the task name for all historic tasks,
sum tasks milestones etc. so that they are displayed in a grey colour.
Elements which are not historic are to be displayed in black font colour as
per Project default.
Our users do not key in completion % nor in any other way flag a task being
completed. Thus in our case a historic element is defined as one where the
current date exceed the finish date.
We are using Project2007 EPM solution.
Thanks in advance
Lars
sum tasks milestones etc. so that they are displayed in a grey colour.
Elements which are not historic are to be displayed in black font colour as
per Project default.
Our users do not key in completion % nor in any other way flag a task being
completed. Thus in our case a historic element is defined as one where the
current date exceed the finish date.
We are using Project2007 EPM solution.
Thanks in advance
Lars