Change gantt to show only 2010 and remove 2009

J

JP

I began a MPP plan in 2009 for a project, certain milestones were met as well
as the loading for 2010. I want to remove Sept-Dec 2009 from the MPP and only
show 2010 for use and reporting purposes.

How can I do this?
 
J

Jim Aksel

We draw a vertical line down the schedule, say on 12/31/2009. Any task in
progress as of that date is split.

Now it become a matter of arranging the remaining work and completed work
into two sections on the schedule. So, you eventually end up with two new
roll up summaries "2009" and "2010". Now collapse the 2009 summary. If you
wish, apply a filter to only show tasks where Finish>1/1/10.

This does involve duplication of the project structure. You then "just"
delete what doesn't belong there and make sure you link it correctly. For
example, you may have a task completing in 2009 that drives the start of
something in 2010.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top