Hi Steve,
You may be changing the data in the wrong place. Try following
the
step-by-step below.
1. Display a resource view (Resource Sheet or Resource Usage)
2. Double click on the resource's name to open the Resource
Information dialog box.
3. On the General tab, click the Change Working Time button to
display the Resource's calendar in the Change Working Time dialog
box.
3. Scroll the calendar to the required month.
4. Click the drag to select the Monday, Tuesday, Wednesday,
Thursday, and Friday dates.
5. Click the Exception tab and enter a name for the exception
(Long
Week for example)
6. Click in the Start or Finish field in that row. (This is just
to
activate the details button)
7. Click the Details button.
8. Click the "Working Times" radio button to populate the From
and
To boxes with the standard 8:00 to 12:00 pm and 1:00 pm to 5:00
pm.
9. Change the 5:00 pm to 9:00 pm and press ENTER.
10. If the Long week repeats on a regular schedule set a
recurrence
pattern of weekly every x weeks and check Monday, Tuesday,
Wednesday, Thursday, Friday
11. Click Ok to close the Details box and return to the Change
Working time. Monday through Friday of the selected week should
now
be blue and you should be able to see the changed working time.
12. Click OK to close the Change Working Time dialog box.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Steve said:
Hi Julie - we're on 2007. I've done all thats been suggested by
everyone. It
doesn't work. Changing 1 specific 5 day (M-F) work week for one
specific
resource from 8a-5p to 8a-9p defaults his entire calendar.
Very
frustrating.
:
Hi Steve,
You don't note what version (2003, 2007) you are using.
Project
2003 is up to Service Pack 3, Project 2007 has service pack 1
and
an
infrastructure update.
If you are using Project 2007 and editing the times, make sure
you
press ENTER before clicking on OK to close the Details dialog
box.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Thanks - thats what I've been doing - but it doesn't take.
One
of
my
colleagues thinks I might be missing some updates. I'll try
to
get
those
uploaded and see if it works then.
Appreciate all the help.
Good weekend to all.
:
Open the resource's calendar and go to the specific weeks
in
question.
Highlight the dates Mon-Fri such as 13Oct to 17Oct in the
first
week and set
the working times for those day to whatever times describe
the
8
hours per
day, for example 8-12 and 1-5. Go to the next week,
highlight
all the
specifc dates and set the hours to the correct time for
those
days, ie, 6-12
and 1-7. do the same for the third week, such as 7-12 and
1-6.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
How do I change the numbers of hours in a work week for
the
specific week?
Ex - Week 1: 5x8 = 40 hrs
Week 2: 5x12 = 60 hrs
Week 3: 5x10 = 50 hrs.
Whatever the last entry is becomes the default for the
entire
calendar for
the resource. I need specific weeks to refelct specific
total
hours.
Thanks
Steve