G
Girija
Hello,
I was viewing a project and found that there is difference in Baseline start
and start, while actual start is NA. Could anyone help me to to understand as
why there is change in the Baseline Start and Start?
Does it mean that after the project is Baselined th eProject Owner has
changed?
If so is there any way that we can rebaseline with the same date?
Thanks
Girija
I was viewing a project and found that there is difference in Baseline start
and start, while actual start is NA. Could anyone help me to to understand as
why there is change in the Baseline Start and Start?
Does it mean that after the project is Baselined th eProject Owner has
changed?
If so is there any way that we can rebaseline with the same date?
Thanks
Girija