Girija
Hello,
I am using MSP 2003. I have baslined a project and some updations have
happened. But I am in a situation, where I have to change some predecessors
(predecessor being the updated task) and rebaseline. But when I am trying to
change the predecessor its not updating the start date.
My doubts are :
1) Can we rebaseline the project where some updations have happened?
2) Why the start date is not getting updated to the new date?
3) What is the best practise in such situation?
Thanks
Girija