Change in Start and Finish Dates

R

R X

Dear Friends,

I m using Project 2007. When I change date in Actual Start and Actual Finish
column, same dates appear in Start and Finish column. Wht is the solution for
this problem...........?
 
G

Gérard Ducouret

Hello,

That is not a problem. That's normal. Maybe what you expected to compare is
the Baseline Start and Baseline Finish.
Before entering any progress information, set the Baseline of your project:
Tools / Tracking / Set Baseline...
Then you can insert the 2 fields or display a table like Variance.
Hope this helps,

Gérard Ducouret
 
D

Doctor Dave

Dear Friends,

I m using Project 2007. When I change date in Actual Start and Actual Finish
column, same dates appear in Start and Finish column. Wht is the solution for
this problem...........?

This is actually the correct behaviour.

If you want the application to remember the original planned dates,
the easiest way is to save a baseline before starting to record
progress.
 