Dear all
I have this problem, maybe someone can help me to give suggestion
I was assigned for one task in
work = 8hr, duration = 1 days
But I can finished my task early, at 8/1/2007 in actual work = 4hr
So I do this, is it correct?
- In My timesheet I update actual = 4hr, submit my timesheet
- Import my timesheet,
remaining work = 4hr, edit with remaining work = 0 hr
percent completed = 50% (4hr from 8hr), edited with percent completed = 100%
-Then I submit task
-But the result is : the planned continues at 8/2/2007.
8/1/2007 8/2/2007
URF 01-Create Spec Actual
Planned 8h
8/1/2007 8/2/2007
URF 01-Create Spec Actual 4h
Planned 4h 4h
What must I do to correct this case?
What must I set to the task has finished early, I done it faster than the
plan. and the percent completed sets 100%
Thanks a lot my friends..for your help
I need it
regard
Dee
I have this problem, maybe someone can help me to give suggestion
I was assigned for one task in
work = 8hr, duration = 1 days
But I can finished my task early, at 8/1/2007 in actual work = 4hr
So I do this, is it correct?
- In My timesheet I update actual = 4hr, submit my timesheet
- Import my timesheet,
remaining work = 4hr, edit with remaining work = 0 hr
percent completed = 50% (4hr from 8hr), edited with percent completed = 100%
-Then I submit task
-But the result is : the planned continues at 8/2/2007.
8/1/2007 8/2/2007
URF 01-Create Spec Actual
Planned 8h
8/1/2007 8/2/2007
URF 01-Create Spec Actual 4h
Planned 4h 4h
What must I do to correct this case?
What must I set to the task has finished early, I done it faster than the
plan. and the percent completed sets 100%
Thanks a lot my friends..for your help
I need it
regard