Y
Yannis
Hello,
we need to set a resource to only work for one (1) day per week on a
specific project (because we want to book the rest 4 days to work in another
project).
[At the Enterprise Pool level, the resource is correctly setup to work five
(5) days per week]
Is there any way we can achieve this?
Thanks in advance, YP
we need to set a resource to only work for one (1) day per week on a
specific project (because we want to book the rest 4 days to work in another
project).
[At the Enterprise Pool level, the resource is correctly setup to work five
(5) days per week]
Is there any way we can achieve this?
Thanks in advance, YP