Change start/end dates

J

jacsdad

when adjusting a start or end date date, I inadvertenly checked the box 'do
not show this message again' Now when I attempt to make a tast start or end
on a non-workday,it reverts to the next workday... ususally the following
Monday.

How can I get this prompt back.

Thanks ahead of time...
 
J

John

jacsdad said:
when adjusting a start or end date date, I inadvertenly checked the box 'do
not show this message again' Now when I attempt to make a tast start or end
on a non-workday,it reverts to the next workday... ususally the following
Monday.

How can I get this prompt back.

Thanks ahead of time...

jacsdad,
I hope you're not "adjusting" start and finish dates by manually
entering them in. Doing so sets a constraint and totally defeats
Project's scheduling engine which depends on a floating linked schedule.

User alerts are set under Tools/Options. There are multiple options for
users alerts. Look at each tab under the options and check appropriate
alerts.

Hope this helps.
John
Project MVP
 