Change Status Manager

  • Thread starter Alexander Barvinsky
  • Start date
A

Alexander Barvinsky

Hi,
How to change Status Manager field for the user name, who last publish the
project? And could somebody describe algorithm which MPS use to fill this
field?
TIA
Best regards,
Alexander Barvinsky
http://pm4pm.org
 
D

Dale Howard [MVP]

Alexander --

The person who last published the project needs to open the project again,
insert the Status Manager field, and then set himself/herself as the Status
Manager for every task. Then he/she needs to save and publish the project.
Hope this helps.
 
A

Alexander Barvinsky

Thank for you letter. Does it mean that Status Manager field automatically
fills with the name of user who add task to the plan with Project
Professional and publish it on the server?
Alexander --

The person who last published the project needs to open the project again,
insert the Status Manager field, and then set himself/herself as the Status
Manager for every task. Then he/she needs to save and publish the project.
Hope this helps.
Best regards,
Alexander Barvinsky
http://pm4pm.org
 
D

Dale Howard [MVP]

Alexander --

Yes, your assumption about new tasks is correct. Hope this helps.
 