D
Darrell
Have Team Members always been able to change the start and finish dates
through the PWA Task Status page when using the “Hours of work done per dayâ€
updating process? Why would this be made available when team members should
only be entering progress and remaining work and not be able to actually
change a task’s start date? I recently had a resource ask why she couldn’t
make a task end on a selected date and only require 40hrs of work. When I
began investigating, I found out that team members could actually change the
start or finish dates of a task and submit the change for approval along with
task progress. Has this always been available or is this new?
Darrell
through the PWA Task Status page when using the “Hours of work done per dayâ€
updating process? Why would this be made available when team members should
only be entering progress and remaining work and not be able to actually
change a task’s start date? I recently had a resource ask why she couldn’t
make a task end on a selected date and only require 40hrs of work. When I
began investigating, I found out that team members could actually change the
start or finish dates of a task and submit the change for approval along with
task progress. Has this always been available or is this new?
Darrell