E
Emily
I am hoping to find a way to have my "task status" change automatically when
the "% complete" field has any value/% entered into it. So to clarify right
now in task status I have several options (not started, in progress,
complete) I would like to be able to have the "task status" field
automatically change to "not started" when the "% complete" field is blank
and when any percentage/value is entered in the "% complete" then have the
"task status" field change to "in progress" and lastly when the "% complete"
field has a value of 100% in it have the "task status" field change to
"complete". Is this possible?
the "% complete" field has any value/% entered into it. So to clarify right
now in task status I have several options (not started, in progress,
complete) I would like to be able to have the "task status" field
automatically change to "not started" when the "% complete" field is blank
and when any percentage/value is entered in the "% complete" then have the
"task status" field change to "in progress" and lastly when the "% complete"
field has a value of 100% in it have the "task status" field change to
"complete". Is this possible?