Change Task Update View

I

IainB

Hi,
I want to add a column to the Task Update view in project server so that I
can compare the Baseline1 dates with the actual dates and find out if people
have taken longer on the task than planned (there doesn't seem to be another
obvious way). I've changed Timesheet view to include this column but can't
find a way to add it to Task Update View.

Thanks
 
D

Dale Howard [MVP]

IainB --

You need to add the Baseline 1 field to the list of published fields in each
project. To do so, complete the following steps:

1. Click Tools - Customize - Published Fields
2. Add the Baseline 1 field to the list on the right
3. Click OK
4. Click Collaborate - Publish - Republish Assignments and then click OK

You must complete the above process for every project in the database, and
should do so for every enterprise project template as well. Hope this
helps.
 