H
Hernandezz
Hi.
I haved seen a lot of posts with questions about how export data from
timescale.
I use project 2007 and my question is about, how to change the
assignment work for a specific resource in a specific day.
Example:
work assignment =40h
duration assignment = 5 days
monday =8h, tuesday=8h...friday=8h
then i want for example change the monday work to 7h, and friday to
9h, all within timescale in resource usage. it's possible with VBA?
Thanks,
Best Regards
I haved seen a lot of posts with questions about how export data from
timescale.
I use project 2007 and my question is about, how to change the
assignment work for a specific resource in a specific day.
Example:
work assignment =40h
duration assignment = 5 days
monday =8h, tuesday=8h...friday=8h
then i want for example change the monday work to 7h, and friday to
9h, all within timescale in resource usage. it's possible with VBA?
Thanks,
Best Regards