R
Rabbit
Hi All,
As a project manager, how can I change the timesheet of a team member if the
team member fill in the wrong working hours?
I can change the actual work hours of a team member on resource usage report
using project professional2003,and public the change to project server, but
the number is not change on timesheet report on PWA, can anyone let me know
what's happen?
Thanks in advance,
Rabbit.
As a project manager, how can I change the timesheet of a team member if the
team member fill in the wrong working hours?
I can change the actual work hours of a team member on resource usage report
using project professional2003,and public the change to project server, but
the number is not change on timesheet report on PWA, can anyone let me know
what's happen?
Thanks in advance,
Rabbit.