Change the timesheet for team member.

R

Rabbit

Hi All,

As a project manager, how can I change the timesheet of a team member if the
team member fill in the wrong working hours?

I can change the actual work hours of a team member on resource usage report
using project professional2003,and public the change to project server, but
the number is not change on timesheet report on PWA, can anyone let me know
what's happen?

Thanks in advance,

Rabbit.
 
R

Reid McTaggart

You need to select the task, then Publish > Republish Assignments > Selected
Tasks, and check the box to overwrite actuals in the resource's timesheet.
--
Reid McTaggart
(e-mail address removed)
Alegient, Inc., Houston
Project Server Experts
Microsoft Certified Partner
 
R

Rabbit

We got the confusion problem when we change timesheet in this way, the
column WWORK_APPROVAL_STATUS in MSP_WEB_WORK table will be changed the
existing "1" value to "null" value, do you know what's happen? does PM still
need to approval the timesheet change from PWA?

Thanks for your help.

Rabbit
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top