Change to Project 2003 Resource Availability View

I

Ian Bertram

At the 11th hour of our Project 2002 to 2003 upgrade we
have found a small change to the Project Web 'View
Resource Availability" page that has significant
implications to our Resource Planning process.

In Project 2002 Web we would select multiple resources
(usually a team) and use the 'View Resource Availablity"
page and "Remaining Availability" view in order to
identify overallocated resources... This is quite easy as
overallocated resources would display with NEGATIVE
Remaining Availaibilty...

In Project 2003 this view (graph) NO LONGER SHOWS
NEGATIVE Remaining Availability on its "y" axis,
negatives are show as zero, therefore no longer showing
you over allocated resources..

Am I missing something here...
 