Change view of Task Reassignment

S

Sachin De

How to change the view of Task Reassignment. I want to add some customised
columns/fields in this view so as to help in undestanding what exactly is
being reassigned.

Please suggest.
 
D

Dale Howard [MVP]

Sachin De --

You cannot change the Task Reassignment page. It is one of the pages that
the Project Server administrator cannot modify. Hope this helps.
 