Change Working Days to Calendar Days without Impacting the Task Dates

M

Melissa San

I have an existing project schedule that I need to change to calendar days. I successfully made the change in the Change Working Time tab but most of my finish task dates automatically adjusted. I want the start and finish dates to stay the same but just the duration to reflect the new dates now that the project is a 7 day work week rather than 5. How can I change to calendar days without impacting my start and finish task dates?
 
M

Mike Glen

I have an existing project schedule that I need to change to calendar days.  I successfully made the change in the Change Working Time tab but most of my finish task dates automatically adjusted.  I want the start and finish dates to stay the same but just the duration to reflect the new datesnow that the project is a 7 day work week rather than 5. How can I change to calendar days without impacting my start and finish task dates?

Hi ,

Welcome to this Microsoft Project forum:)

I suspect you have a mismatch with the settings. First, have a look
at FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be
seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP (97-11)
See http://tinyurl.com/2xbhc for my free Project Tutorials
 