Change working time days by task

G

George Wilson

I am using Project 2002 standard edition. I would like to
be able to change the working days to weekedns for certain
tasks as they arise and the resources are available. When
I change working time the project is changed globally
within the project. Can this be changed by task or
resource or does it have to be changed globally?
TIA
George
 
J

Jan De Messemaeker

Hello George

It can be changed by task and/or by resource
Both will have priority over the project calendar
For resources: Double-click on the resource in the resource sheet, select
Working time
For tasks: Tools, Change Working time, select New for a new calendar, give
it a name, modify it a snecessaryu, then in Task Information for the task,
Advanced Tab, Calendar, select the appropriate one.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA