Change working time globally in Project Server

S

Steve C

Hi,

How does and admin change the Global working time to account for holidays
and such for an entire enterprise?

Thanks,


Steve
 
J

Jack Dahlgren

They check out the enterprise global and modify the "Standard" calendar.
Or create a company calendar and set that as a default for all projects.

-Jack Dahlgren
 