D
Dori
I am working on a stand alone copy of Project Standard 2002. I have multiple
projects running with separate project calendars. I would like to update the
calendar for a particular project to reflect all days that the project team
as a whole is not working.
Some of the project calendars update and save via Tools->Change Working
Time, selecting the day and selecting nonworking time. However a few of the
plans will change while I have it up. Once I save, close the project, and
reopen it, none of the dates I entered are listed as nonworking days.
I have also tried to copy the calendars from the projects that were able to
save the information. But the information is still missing when I open it.
What is happening that is different between the two projects? How can I get
the calendar to recognize the additional nonworking days?
projects running with separate project calendars. I would like to update the
calendar for a particular project to reflect all days that the project team
as a whole is not working.
Some of the project calendars update and save via Tools->Change Working
Time, selecting the day and selecting nonworking time. However a few of the
plans will change while I have it up. Once I save, close the project, and
reopen it, none of the dates I entered are listed as nonworking days.
I have also tried to copy the calendars from the projects that were able to
save the information. But the information is still missing when I open it.
What is happening that is different between the two projects? How can I get
the calendar to recognize the additional nonworking days?