T
Texasroy
I am trying to do what ifs on the working time needed to complete a number of
tasks (which can all be done immediately - no dependencies). I have set the
tasks as "Fixed Work" and the total work is 1720 hours. With one resource on
a 5 day, 8 hour per day calendar with no holidays, I get the expected 215
days duration when I level for the one resource (1720 divided by 8). I want
to set the availability to be 10 hour days, then 12 hour days, then 8 hour
with a 6 day work week, 10 hours with a 6 day work week and finally 12 hours
with a 6 day work week. When I go to set the 10 hours (change working time,
Options, Default Start time I set to 7:00 am and end time to 6 pm and I also
set the workweek default to match. However, I have noticed that when I go
right back into the Change working time, the 7 am held, but the 6 pm doesn't,
it has returned to 5 pm. When I level I get 192 working days (9 hours per
day). What gives?
tasks (which can all be done immediately - no dependencies). I have set the
tasks as "Fixed Work" and the total work is 1720 hours. With one resource on
a 5 day, 8 hour per day calendar with no holidays, I get the expected 215
days duration when I level for the one resource (1720 divided by 8). I want
to set the availability to be 10 hour days, then 12 hour days, then 8 hour
with a 6 day work week, 10 hours with a 6 day work week and finally 12 hours
with a 6 day work week. When I go to set the 10 hours (change working time,
Options, Default Start time I set to 7:00 am and end time to 6 pm and I also
set the workweek default to match. However, I have noticed that when I go
right back into the Change working time, the 7 am held, but the 6 pm doesn't,
it has returned to 5 pm. When I level I get 192 working days (9 hours per
day). What gives?