Veronica
Hi,
I have updated the enterprice resource pool to reality. Every resource
calendar is now up to date according to everyones working hours. This could
differ a lot. Some are working 20% and some 100%.
I then realized that this affected the project plans in such a way that the
duration of the tasks were lengthened. I thought the resources would be
"overallocated" since the task type is set to "fixed duration" . But of
course, we have set a unit of the resources available hours in the project
plans. I suppose that is why the duration is lengthened?
How should I do this if I rather want the duration to be fixed in plans and
the resources unit to increase (and even get overallocated) when I decrease
the working hours in their calendars?
Many Thank´s /Veronica
I have updated the enterprice resource pool to reality. Every resource
calendar is now up to date according to everyones working hours. This could
differ a lot. Some are working 20% and some 100%.
I then realized that this affected the project plans in such a way that the
duration of the tasks were lengthened. I thought the resources would be
"overallocated" since the task type is set to "fixed duration" . But of
course, we have set a unit of the resources available hours in the project
plans. I suppose that is why the duration is lengthened?
How should I do this if I rather want the duration to be fixed in plans and
the resources unit to increase (and even get overallocated) when I decrease
the working hours in their calendars?
Many Thank´s /Veronica