Hello,
is possible to detect which tasks were changed after leveling? I mean some
sort of "inteligent" detection - not to compare 2 snapshots - before and
after leveling. The Project 2007 Prof is able to show it in GUI, but is it
possible to detect changed tasks programatically - after few days of
investigation I'm still not able to find appropriate algorithm?

Thanks for help.

Best regards,
David Mensik.
 
J

Jack Dahlgren MVP

Have you looked at the task.levelingdelay property? It should be non-zero
for tasks which are leveled.

-Jack Dahlgren
 
J

Jan De Messemaeker

Hi,

Leveling delay doesn't fully answer the question I'm afraid.
When a task is moved by leveling it has a leveling delay.
but when because of that his successor gets delayed, that one will NOT show
a leveling delay since it is the link that made it move, not leveling itself

The full answer is as follows
Before leveling do EXPLICITLY clear leveling
Then after leveling compare Preleveled Start to Start.
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top