Using a technique provided to me from this (great) discussion group, I have
been able to create some spreadsheets to determine those resourcesthat are
not submitting hours to the Project Managers regurlarly. This is done as
follows:
* Resource Central
* View Resource Assignments
* Select desired resources and click apply
* Auto Filter and filter on "Changes Not yet Submitted"
What I am finding is that this produces a view shows ALL hours - and the
actual changes that have not yet been submitted appear in red. When I
export this to excel, I lose the color "red" - thus rendering the spreadsheet
useless when sending on to others. Is there any way to ONLY see the changes
that have not yet been submitted?
been able to create some spreadsheets to determine those resourcesthat are
not submitting hours to the Project Managers regurlarly. This is done as
follows:
* Resource Central
* View Resource Assignments
* Select desired resources and click apply
* Auto Filter and filter on "Changes Not yet Submitted"
What I am finding is that this produces a view shows ALL hours - and the
actual changes that have not yet been submitted appear in red. When I
export this to excel, I lose the color "red" - thus rendering the spreadsheet
useless when sending on to others. Is there any way to ONLY see the changes
that have not yet been submitted?